Work Projects Page - 2022 +

Work Projects - Items in Descending Year order
  (back to Home Page)

2023  Work Projects
  (back to Home Page)

2023 - Tilley Road Upstream Project

( There is one mile of the North Fork of the Ditch from just north of the Stroble parcel to the Culvert at 93rd Ave.) 

This project is undertaken to deal with the January 2022 Flood and increased flow.
Goal: Re-establish the Ditch using LiDAR to determine "ditch-line" and extend it through the newly annexed parcels giving a defined channel for the increased water coming from
above the prior Ditch.


2022 Work Projects  -  (Details about the work done in 2022  -  INCLUDING End of Year Accounting)
  (back to Home Page)

2022 - Tilley Road Upstream Project

(we were able to get all the way to just north of the Stroble parcel in the Main Fork of the Ditch and we also were able to upgrade the Culvert beside Tilley Road/SR-121 to try to eliminate flooding/overflowing of SR-121 )

This project is undertaken to deal with the January 2022 Flood.

Goals: Remove debris and silt brought into ditch from flood and increase capacity of Ditch. (see pictures for specifics)


 2022 Blomberg Narrowing

(also removed 2 beaver dams and a tree that had fallen into the Ditch down-ditch)

There is a noticed "Ditch Narrowing" that is reducing flow that needs repair here

This project was accomplished without any cost to the Ditch District because the landowner volunteered to use his equipment and time! This is Greatly Appreciated!